Fano Creek Bank Stabilization

Restoration Fano Creek Bank Stabilization

Project Summary

Fano Creek had been undercutting the bank below these multi-family structures. As part of the long term resilience within the drainage, scour protection was needed to keep these residence’s from slough- ing into the creek.

Evergreen Developers was sub contracted to assist in the excavation and placement of rip rap on this slope.

Key Elements

  • Temporary dams and diversions
  • Bank stabilization
  • Rip rap placement

Contracting Agency

City of Tigard & Henderson LLC

Industry Sector

Ecological Restoration, Bank Stabilization

Location

Cathlamet, WA